Three administration buildings on the Mesa Grande Reservation in San Diego County, California, are now served by solar and battery storage systems, completing a project the Mesa Grande Band of Diegueño Mission Indians developed with the nonprofit Solar Electric Light Fund (SELF). The Tribe described the installation as the first public clean energy project on the reservation and another step in a longer effort to exercise greater control over its energy supply.
The systems supply the Tekamuk, Hallyeyaaw and Golden Eagle administration buildings, which the Tribe says act as civic and community hubs. The buildings house tribal government functions and housing services and host cultural and educational activities, food distribution and emergency response operations.
Designed capacity and savings
According to the Tribe, the systems were sized to cover the three facilities' present electricity demand while leaving room for future growth. The stated performance expectations are:
- Combined solar generation of roughly 60 MWh per year across the three buildings.
- Electricity cost savings of at least $16,780 annually.
- Battery storage that allows the administration buildings to keep operating independently of the grid when power is interrupted.
The resilience element carries particular weight in a rural community where interruptions are routine. Curtis La Chusa, chairman of the Mesa Grande Tribal Council, said electricity tends to go unnoticed until it fails, and that at Mesa Grande outages can stretch for days at a time, disrupting the services the Tribe provides to its members.
Two decades of energy work
The project follows a long history of limited grid access. Electricity did not reach the reservation until the 1950s, and some homes still are not connected, relying on small generators for basic household needs. Over the years the Tribe has pursued residential solar, renewable energy planning and workforce development.
That workforce work fed directly into the installation: four Tribal members who had previously completed solar installation training were employed on the project, according to the announcement.
Bob Freling, executive director of SELF, which facilitated the project, said reliable and affordable energy gives communities room to invest in what comes next, and that lower energy costs and stronger resilience can free up resources while laying a foundation for growth.
Groundwork for a housing build-out
The clean energy installation coincides with the start of the Tribe's long-term planning for new housing and community infrastructure. That plan contemplates 1,500 new homes intended to address affordability and supply shortages that have historically limited how many members can live on Tribal land. It would include the first new housing built on the reservation since 2005.
La Chusa linked the energy work to that broader ambition, describing a future in which members can return home and find the spaces and services needed to thrive.
Funding for the project came from the William, Jeff and Jennifer Gross Family Foundation and other donors, according to the announcement.